CPL HVAC Mechanical Equipment Installation

CPL HVAC Mechanical Equipment Installation

  • This project was for the ExxonMobil Chemical Plant Laboratory in Baton Rouge, a critical operation for the ExxonMobil complex. It took 13 months to complete in a fully occupied and operating laboratory without interruptions to business operations. Moore was able to complete the project five months ahead of schedule.
  • The entire HVAC and exhaust ventilation systems were revamped. This included new air handling equipment, rooftop packaged units, steam to hot water heat exchangers, humidity controls, chilled water pumps, chilled water piping, ductwork modifications, and instrument controls. Moore’s personnel self-performed all scope items except for insulation work.