Linde

Project Stats

Contract Value: $4mm

Services Provided

  • Civil

This project consisted of constructing two air bridges over seven active pipelines to support the transportation route of modular production units. The bridges were designed and constructed to handle significant load requirements while maintaining uninterrupted pipeline operations below.

Project Details

  • The deep foundations included driving 66EA, 24″ auger cast piles in between and around 7 active pipelines.
  • The concrete foundations included pile caps, and cast-in-place walls and anchor bolts for steel girders.
  • Moore lifted and installed girder units totaling 200 tons of structural steel, and precast concrete panels onto the steel girders.
Interior of a large industrial warehouse with high ceilings, multiple overhead cranes, and exposed beams in a shop for maintenance buildings.
background metal texture

Let's discuss your project

Contact us today to see if Moore Industries can assist you with your construction project.

Reach Out Today Reach Out Today