CF Industries AM5 Civil & Structural Upgrades

CF Industries AM5 Civil & Structural Upgrades

  • This project included lifting an 85,000 lbs Substation building with a 500-ton crane (over existing buildings) and placing on top of 9 ft concrete piers that were installed by Moore’s Team.
  • Moore demoed the existing buildings then self- performed the new foundation work and new steel work including leveling channels for new switchgear, miscellaneous cable tray supports, bulkhead steel, and a new double door with transom.